RoadWork

As per Special Meeting of Council held May 2, 2024 a few updates to look forward to include:

1. Public Works Capital Project $240,000 is scheduled for May and June.

This will include culvert replacements and improvements, ditch improvements road crown improvements gravel on roads calcium chloride dust suppressant.

A detailed timeline and project description will be out ~May 13 depicting where and when the roadwork and ditching will be occurring. Please note frost boils on Rangeline will be addressed as ground thaws.

Rangeline Road project originally tendered in January 2024 for resurface and possible paving resulted in bids ~ 1.1 million dollars and thus has been voted down. Detailed plans including dates for 2024 roadworkd will be out ~ May 13.